STS Crane Size Configurator

Crane elevation / vessel cross-section
Ship to the left · equal horizontal & vertical scale · rail elevation = 0
Geometry preview
Trolley limits / max spreader heightRequired lift / selected rowGeometry shortfallGantry travel: along quay, into / out of this view
Outreach reserve
Lift height reserve
Rows within reach
Row centers within trolley limits
Maximum outreachRear trolley limit

Loading the Engineering Notice. Controls remain disabled until acknowledgement. If the notice does not appear, reload this page to retry.

Engineering considerations

Vessel trim and list are not included in this geometric model. Additional outreach and lift-height allowances may be required to accommodate vessel attitude and operating conditions. Verify all dimensions and clearances against project-specific requirements.

Wheel load estimate assumptions

Estimated individual wheel loads use the documented gantry assumption of eight wheels per corner and are reported in metric tonnes (metric tons) as mass-equivalent values, using 9.81 kN per metric tonne. Actual wheel loads depend on project-specific owner requirements, wind loading, the final crane arrangement and design assumptions, and applicable operating and loading conditions. These are preliminary planning estimates only, not a substitute for detailed engineering design. Final loads must be established through detailed engineering and verified crane manufacturer information.

The online wheel-load formulas apply to conventional single-trolley STS cranes only. Dual-trolley cranes require separate engineering evaluation.

Ship-to-shore crane outreach and lift height planning

This STS crane size calculator compares selected crane outreach and container crane lift height with illustrative vessel and berth geometry. Use it for preliminary crane sizing for container vessels and terminal layout studies.

Required outreach is measured from the waterside rail to the farthest container-row center. It includes rail setback, the ship-to-quay gap, and the centered container bank within the modeled vessel beam. Required lift height is the stack top above rail elevation plus one lifted container height; it depends on moulded depth, draft, water level, and on-deck tiers. Reserves are selected crane dimensions minus these geometric requirements. Negative reserves indicate a geometric shortfall.

Common Planning Questions (FAQ)

How can I estimate STS crane wheel loads?

Preliminary STS crane wheel loads can be estimated with a simplified crane model and an assumed load distribution. CP&A provides an estimated wheel-load feature within the STS Crane Size Configurator, using outreach, lift height, rail gauge, and backreach with a documented gantry assumption of eight wheels per corner. Results are individual-wheel estimates; the tool does not separately calculate wheel-by-wheel load distribution. A CP&A Engineering Tools account is required to access the estimates. Use them for preliminary planning and comparison, rather than final crane or quay structural design.

What factors affect ship-to-shore crane wheel loads?

Wheel loads depend on crane configuration and geometry, crane dead weight and load distribution, gantry wheel arrangement, operating and lifted loads, wind loading, owner requirements, and applicable loading conditions and design assumptions. This tool uses four geometry inputs and provides landside and waterside estimates for operating, low-wind overload, and high-wind overload cases. It does not separately calculate crane dead weight or accept project-specific lifted loads, wind speeds, or wind pressures. The case labels do not represent a project-specific wind analysis. Crane type, additional dual-trolley equipment, and other project-specific effects require separate engineering verification.

Can preliminary STS crane wheel loads be used for quay or wharf design?

Simplified wheel-load estimates can support early-stage planning and comparisons, but they are not final design loads and do not establish quay or wharf structural adequacy. Final design requires project-specific crane wheel loads and appropriate load cases covering the relevant environmental and operational conditions. Qualified engineers and crane manufacturers must verify the design values, loading conditions, and applicable project requirements.

What size STS crane do I need for a 24-container-wide vessel?

Container-row count alone does not define an appropriate crane specification. Ship-to-shore crane sizing depends on required outreach and lift height, as well as operational requirements that this geometric model does not assess. Vessel beam and container-row arrangement, waterside rail position and setback from the quay face, ship-to-quay clearance, vessel draft, and on-deck stack height all affect the preliminary geometric requirements.

Select the illustrative Megamax-24 preset, review the vessel and berth inputs, and compare the required dimensions with your selected crane outreach and lift height. Use the reserves and rows within reach to explore geometric fit; qualified crane engineers must verify the dimensions, assumptions, clearances, and operating allowances before a crane specification is established.

How much crane outreach is required for a 24-row container ship?

Required outreach is the horizontal distance from the waterside crane rail to the center of the farthest container row, not the hull side or outer container edge. The model includes rail setback from the quay face, the ship-to-quay gap, and the container bank centered within the modeled vessel beam. Beam is derived from row count, row pitch, and the preset's illustrative beam allowance.

There is no universal outreach dimension for all 24-row vessels and berths. Review the required outreach shown beneath Outreach reserve. The reserve equals selected crane outreach minus required outreach; a negative value indicates a geometric shortfall. Row pitch, vessel geometry, and berth offsets must reflect the project being evaluated.

How is the required lift height of a ship-to-shore crane determined?

The model approximates deck elevation using vessel moulded depth minus draft, adjusted for water level relative to the rail datum. Actual water level above rail is the water-level change minus rail elevation above reference water. The modeled quay surface is at rail datum zero; a separate quay-to-rail elevation difference is not included.

On-deck tier count multiplied by container height is added to the deck elevation to obtain the stack top above rail. Required lift height then adds one more container height to represent a lifted container above the stack. This is a modeled geometric allowance for the lifted container, not a general operating-clearance allowance.

Additional operating and clearance allowances may be necessary. Vessel trim and list are not included. Qualified crane engineers must verify all dimensions, assumptions, clearances, and project-specific allowances; this calculation is preliminary geometric planning, not detailed engineering verification.

Can this configurator be used for 26-row container vessels?

Yes, for conceptual comparisons. Select Future Ultra-Large (26 Rows), which is an illustrative future-planning scenario rather than a verified vessel design. Compare it with Megamax-24 to explore crane outreach for 24-row and 26-row arrangements, required lift height, outreach and lift-height reserves, and rows within reach.

Both presets use illustrative planning assumptions. Review row pitch, stack height, vessel draft, and berth offsets for each comparison; neither preset establishes a suitable crane specification.

How do berth conditions affect container crane lift height?

Higher water levels raise the vessel relative to the rails, while greater draft lowers the modeled deck. A higher rail elevation above reference water reduces the modeled stack elevation relative to the rail datum. More on-deck tiers or taller containers increase required lift height. Compare scenarios using the vessel and berth controls, and verify the relevant water levels and operating conditions for the project.

Does a positive outreach or lift-height reserve establish crane suitability?

No. A positive reserve indicates additional geometric reach or height beyond the modeled requirement. This preliminary model does not verify lifting capacity, structural strength, vessel stability, collision envelopes, or operating limits, and it does not establish safe crane operation. Detailed suitability assessment requires vessel-specific and project-specific checks by qualified crane engineers, including trim, list, and appropriate operating allowances.

Usage Analytics & Privacy

CP&A measures how often its engineering tools are opened, which controls are adjusted, when vessel presets are changed, how often diagrams are exported, and how often visitors see or acknowledge the configurator welcome screen or return to Tools from it. For page openings and welcome events, we may also record an approximate country and state or province based on network location.

The ton calculator records page openings and approximate country and region only; it does not track calculator inputs or interactions. These statistics help us understand which tools are useful and where improvements are needed. We do not intentionally collect names, IP addresses, visitor identifiers, precise locations, or exact engineering configurations.

Usage analytics are off.

Read the full usage analytics disclosure

Full usage analytics disclosure

We count page openings, completed control adjustments, vessel preset changes, diagram export initiation, and welcome-screen displays, acknowledgments, and Back to Tools actions when analytics permission applies. Acceptance is not analytics consent and is not a unique-visitor count. Adjustment records include only a predefined control name, not its value. Page-opening and configurator welcome-event records may include an approximate country and first-level state, province, or comparable subdivision supplied by Cloudflare. Other interaction records contain no geographic categories. We do not intentionally store IP addresses, cities, postal codes, coordinates, names, email addresses, visitor or session identifiers, exact dimensions, full configurations, or browser fingerprints. Network location can be inaccurate, especially with VPNs or mobile and corporate networks. Records have service timestamps; low-volume geographic categories may still be identifying when combined with other information. These records are privacy-minimized, not guaranteed anonymous.

Where an approved regional policy permits aggregate measurement, it is enabled unless you turn it off. Elsewhere, optional analytics require your explicit permission. You can withdraw permission or opt out here at any time. Prior refusal and Global Privacy Control are respected. Engineering acknowledgment is independent of analytics permission.

We store your privacy choice and guest engineering acknowledgment locally without an identifier. When signed in, your engineering acknowledgment is also stored privately with your account, notice version, recording time, and whether it was carried forward from this browser. A browser acknowledgment does not independently prove who accepted it. These account records are separate from analytics. Appearance preferences are also stored locally; these are not sent to analytics. Withdrawal stops future events and cancels pending submissions where possible; records already received cannot be recalled.

Cloudflare Web Analytics is a separate service. These preferences apply to custom usage analytics on the Engineering Tools homepage, STS configurator, and ton calculator. Cloudflare handles the network information needed to receive requests separately from our event records.

When you choose to save a named engineering configuration, its inputs and display settings are stored privately in your Supabase-backed CP&A account. Your last-used length units are also stored with your account. These account records are separate from usage analytics. You can delete saved configurations through My configurations.

The company-wide CP&A Privacy Notice link is pending review. This disclosure describes Engineering Tools usage analytics.

Welcome to the STS Crane Configurator

Explore how crane outreach, lifting height, and vessel dimensions come together.

Adjust the settings, compare configurations, and see how different crane sizes accommodate container vessels.

Before you start

This interactive tool is intended for preliminary planning and visualization. It does not account for vessel trim or list, or verify structural adequacy, operational clearances, or crane suitability. Results must be independently verified by qualified engineers before use in design, procurement, or operations.

View complete engineering assumptions and limitations

Engineering acknowledgment is separate from optional analytics. Analytics preferences & privacy

← Back to Tools